Create a Website Account - Manage notification subscriptions, save form progress and more.
During the installation of the new sidewalk at the Historic Courthouse, several issues were discovered on the north side:
We are on the edges of root balls for six trees due to ADA required elevation and slope of new sidewalk. The cut of this elevation caused an earth curb. The plans call for this to be sloped closer to the trees causing more damage to the root ball. Putting a concrete curb on this radius will cause water to sheet flow on to the court square causing flooding potentially.
After discussions, the general contractor, grading contractor, arborist and County project manager, agreed on the best course of action:
County is looking at options to plant a tree in the area during final landscaping. Additionally, the arborist will trim and shape the remaining 13 trees while on-site and a plan is in place to perform root injections on all trees at the end of the project.
Work has begun on installing the historic windows to preserve architectural integrity with the main focus on historical accuracy.
The new water lines at the Historic Courthouse are nearly complete. In the meantime, the City of Lincolnton will provide a temporary water connection until the final tie-in. Landscaping renovations are ongoing—tree removal has been completed, and the arborist will continue assessing the condition of the remaining older trees. Project leaders also reviewed the replacement window glass to ensure it aligns with the original approval from the Historic Preservation Commission.
Progress continues on the Historic Courthouse Renovation as work has now shifted to the surrounding grounds and utility infrastructure. In collaboration with Lincolnton City Public Works staff, contractors are beginning work on installing new water lines and grading the site as part of the planned improvements.
To safely accommodate this phase of construction, the perimeter fence has been moved closer to the curb. The Veterans and War Memorials have been carefully relocated for safekeeping during this portion of the project. Additionally, the bike racks will be relocated during the upcoming portion of the project as well.
A number of trees on the property identified by engineers as decaying, overcome with disease, or impacted by utility work are being removed. These will be replaced with several healthy new trees to enhance the landscape.
Erosion control measures are also being implemented to protect the site during construction. Looking ahead, the next major phase of the project will involve waterproofing the courthouse basement.
The Veterans and War Memorials located at the Historic Courthouse have been temporarily relocated as renovations continue Lincoln County Veterans Services will provide secure storage for the monuments. Upon completion of the courthouse renovations, the monuments will be reinstalled in a newly constructed concrete plaza adjacent to the clock, where the bench will be accessible for use, creating a significantly improved space.